Commercial Refrigeration·Tequesta, Florida

Walk-In Cooler Installation in Tequesta, FL

2R Cooling replaced a commercial walk-in cooler in Tequesta, from removal of the old enclosure to assembly of the replacement box and installation of one condensing unit, two evaporators and copper refrigerant piping. Explore the job through ten real project photos.

Stocked cooler interior — A later view of the replacement enclosure, installed evaporators, lighting and beverage shelving.

Project at a Glance

Location
Tequesta, Florida
Site type
Retail beverage cooler
Enclosure
Customer-supplied replacement walk-in cooler
Configuration
One condensing unit and two evaporators
Scope
Demolition, enclosure assembly and refrigeration installation

Project overview

2R Cooling removed the original enclosure, assembled the customer-supplied replacement box, installed one condensing unit serving two evaporators, ran the copper refrigerant piping and started the system.

Documented work

  • Removed the original walk-in cooler enclosure and cleared the footprint for the replacement box.
  • Assembled the customer-supplied walk-in cooler enclosure.
  • Installed two evaporators inside the cooler and the associated refrigeration equipment.
  • Ran copper refrigerant piping between the installed equipment and prepared the piping work for brazing and vacuum procedures.
  • Started the system.

From the original enclosure to the stocked cooler

The photo sequence documents removal of the original enclosure, the cleared footprint, wall and ceiling assembly, mounted evaporators and piping, work at the outdoor controls, and a later view of the stocked cooler interior.

Planning a similar walk-in cooler installation

For a new or replacement walk-in cooler, share the box dimensions, available equipment specifications, site access and known existing conditions. Those details help define the enclosure, equipment and refrigerant-piping scope before work is scheduled.

Walk-in cooler replacement: before and installation photos

Before replacement — The existing cooler interior and shelving.
Demolition — The existing cooler enclosure being dismantled.
Demolition — The exposed wall and floor area before the replacement enclosure was assembled.
Enclosure assembly — Replacement insulated wall panels being installed.
Enclosure assembly — Ceiling panels and glass-door frontage during the build.
Refrigeration installation — Two evaporators mounted inside the replacement cooler.
Refrigeration installation — Evaporators and piping in place while interior work continued.
Refrigeration installation — Copper piping at the evaporators.
Refrigeration installation — Technician working at the outdoor condensing-unit controls.

Planning a Walk-In Cooler Installation?

Call 2R Cooling or request service to discuss box dimensions, equipment specifications, site access and current scheduling availability.